Secure -
ID #13694
Version #6 -
1/25/2019
|
Scheduling Contact(s) |
Elizabeth Rios Brenner |
shipsked*%*%*ucsd^%^%^edu |
(858) 534-2841 |
|
|
Notes: |
|
10/5 Added a demob day in San Diego for OSU coring gear and Naif's EM instrumentation. 10/11 Added a Jason Engineering dive to Solomon/Torres. 01/10 Adjust Solomon cruise due to delay in Jason shipment. 1/16 Delay intermediate stop in Wellington to reflect additional delays in Jason gear arrival to New Zealand. Extend sea time by one day and reduce port day(s) at end of the second cruise to make up for time lost. Per agreement with chief scientist, 21 February will be a shared Jason offload and Samer Naif load out. 1/25 The Jason equipment is currently being loaded and secured on deck. Due to weather departure for leg two has been postponed by a day. |
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 14 Dec 2018 |
Dep: | 16 Dec 2018 |
Arr: | 13 Jan 2019 |
Unload: | 14 Jan 2019 |
|
|
|
|
|
|
|
|
Samer Naif
|
|
13/14
|
Clearances: New Zealand(A) |
|
|
|
Notes: We are requesting (2) legs with 10 to 30 days between each leg. The first leg will require 28 days, and the second leg requires seven days (both including transit time out of Wellington, NZ). But the time between legs is flexible. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 15 Jan 2019 |
Dep: | 17 Jan 2019 |
Arr: | 26 Jan 2019 |
Unload: | 26 Jan 2019 |
|
|
|
|
|
|
|
|
Evan A. Solomon
|
|
10/12
|
Clearances: New Zealand(A) |
Ancil Facs: Jumbo Piston Coring, Jason |
|
|
|
Notes: Jason winch and misc. shipment to Wellington delayed due to fumigation issues in addition to delays in carrier sail dates.
Shorten port days by 2, load coring equipment, science equipment and partial Jason gear. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 27 Jan 2019 |
Dep: | 27 Jan 2019 |
Arr: | 19 Feb 2019 |
Unload: | 20 Feb 2019 |
|
|
|
|
|
|
|
|
Evan A. Solomon
|
|
24/25
|
Clearances: New Zealand(A) |
Ancil Facs: Jumbo Piston Coring, Jason |
|
|
|
Notes: Load remaining Jason gear.
Share Samer Naif's load out day 21 February to complete Jason offload. Extend sea time by one day, reduce in port time by one day. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 21 Feb 2019 |
Dep: | 22 Feb 2019 |
Arr: | 02 Mar 2019 |
Unload: | 03 Mar 2019 |
|
|
|
|
|
|
|
|
Samer Naif
|
|
9/11
|
Clearances: New Zealand(A) |
|
|
|
Notes: Samer Naif has agreed to share load out day 21 February to complete Jason offload. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 04 Mar 2019 |
Dep: | 04 Mar 2019 |
Arr: | 25 Mar 2019 |
Unload: | 26 Mar 2019 |
|
|
|
|
|
|
|
|
Bruce Appelgate
Transit Cruise
|
|
23/24
|
Clearances: French Polynesia(T), Cook Islands(T), Kiribati(T) |
|
|
|
Notes: Cross Date Line gain a day.
N00014-16-1-2745
Depending on SOA could arrive as early as the afternoon of 3/23/2019
One on home port charge day was added for offload. |
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 27 Mar 2019 |
Dep: | 27 Mar 2019 |
Arr: | 10 Apr 2019 |
Unload: | 10 Apr 2019 |
|
|
|
|
|
|
|
|
Stephen Z. Kelety
Out of Service
|
|
15/15
|
Clearances: NONE(T) |
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 11 Apr 2019 |
Dep: | 11 Apr 2019 |
Arr: | 15 Apr 2019 |
Unload: | 15 Apr 2019 |
|
|
|
|
Vigor Portland/ |
NP09 |
NP09 |
|
|
|
|
|
Stephen Z. Kelety
Transit Cruise
|
|
5/5
|
Clearances: US EEZ(T) |
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
|
|
|
|
Dates |
|
Ports |
|
Area/Navy Op |
|
Lat/Lon |
|
Chief Scientist |
|
Activity/Total Days |
Load: | 16 Apr 2019 |
Dep: | 16 Apr 2019 |
Arr: | 31 Dec 2019 |
Unload: | 31 Dec 2019 |
|
|
|
|
Vigor Portland/ |
NP09 |
NP09 |
|
|
|
|
|
Stephen Z. Kelety
Overhaul or Repair
|
|
260/260
|
Clearances: US EEZ(T) |
|
Project
|
PI/Institution
|
Project #
|
Days/Agency/Status
|
|
|
Notes: Mid Life overhaul through 14 April 2020 |
|
|
|
|
|
Agency
| |
Funded
| |
Pending
| |
Total
|
NAVY
| |
14
| |
0
| |
14
|
NSF
| |
72
| |
0
| |
72
|
Total
| | 86 | | 0 | | 86 |
|
<
Day Type
| |
Total
|
Transit Cruise
| |
28
|
Overhaul or Repair
| |
260
|
At Sea for Science
| |
56
|
Out of Service
| |
15
|
Total
| | 359 |
|
<
Load/Unload Days
| |
Total
|
ChargeLoad
|
|
3
|
ChargeUnload
|
|
4
|
Total
| | 7 |
|